Change Request Management
#

Introduction
#

Project is an instrument of change. Hence during the project lifecycle changes are inevitable. Therefore Change Request in Project Management is an extremely important process in any project. Uncertainties in a project can be managed by using the concept of “Progressive Elaboration” and “Rolling Wave Planning” techniques. As a project manager, you must understand that how much agility is affordable and acceptable. For example in a one-year-long project, if you decide that you will make only a monthly plan and not anything beyond this period (because many things can change in one year period), then what is the guarantee that this one-month plan will not change during execution? Absolutely no guarantee!

What is the Meaning of Change
#

PMI’s PMBOK helps us handling the change request very carefully throughout the project. As per PMBOK change request is any deviation from the plan which you need to follow in order to make a project successful. Therefore change requests can be related to baselines (scope, schedule, cost, quality), plan (risk, communication, resources, procurement, etc), project documents (design, RTM, issue register, risk register, procurement document, etc), organization process assets (OPA), and enterprise environmental factors (EEF). PMBOK 5th edition has defined 47 processes and out of those 16 processes can issue change request at any time in the project life-cycle. And there is only one process that can integrate all change requests and this process is “Perform Integrated Change Control” (PICC)

What is Change Management Process?
#

PICC process of the PMBOK suggests the following steps to process a change request. The first step is to review the change requests. Review includes.

  1. Ensure that the change request is properly understood.
  2. Assigns urgency to the change request (e.g. immediate, next week, next release, etc.)
  3. Assigns type to the change request ( e.g. resources, training, scope, quality, tools, etc.)
  4. Assigns source to the change request (e.g. Security, IT Infrastructure, Customer, Management, Sponsor, Marketing Team, etc.)

The next step of the PICC process is CR is assigned to an expert(s) for the evaluation. After this expert(s) evaluates the change request. Evaluation includes.

  1. What are the other existing systems CR is affecting? For example, the sponsor has CR where he is requesting to assign a full stake developer (FSD) to the project team. As of today when FSD is not there then what are the problems that a team is facing?
  2. How serious is the CR? Does it justify the urgency set by the CR raiser?
  3. What is the impact if a CR is accepted? For example, If FSD is hired and assigned to the team then what needs to be done before he is injected in the midst of the project. What are the consequences of this hiring?
  4. Estimates the financial cost (impact) of this CR.

After this evaluation CR is forwarded to a “Change Control Board”. The size of the impact of the change may be small, medium, or huge. The impact of the change may on architecture, cost, schedule, quality. Depending upon the size and complexity of a project, a project can have multiple layers of “Changer Control Board” CCB. Depending upon the power/authority of the CCB a CR is forwarded by the PM to an appropriate CCB. The CCB makes the final decision to accept or reject the change request.

Whatever is the final decision of CCB, PM updates project documents and project plan accordingly and assign the work project team. The project team implements change requests and the implementation of CR is verified by the quality team.

PMBOK Processes for Change Management
#

As per PMBOK 5th Edition following 16 processes can raise change requests. These processes are part of different process groups. The 17th process which handles all the CR is Perform Integrated Change Control (PICC) is not listed below.

1Direct and Manage Project WorkExecuting
2Perform Quality AssuranceExecuting
3Manage Project TeamExecuting
4Conduct ProcurementsExecuting
5Manage Stakeholder EngagementExecuting
6Monitor & Control Project WorkMonitoring & Controlling
7Validate ScopeMonitoring & Controlling
8Control ScopeMonitoring & Controlling
9Control ScheduleMonitoring & Controlling
10Control CostMonitoring & Controlling
11Control QualityMonitoring & Controlling
12Control CommunicationsMonitoring & Controlling
13Control RisksMonitoring & Controlling
14Control ProcurementsMonitoring & Controlling
15Control Stakeholder EngagementMonitoring & Controlling
16Plan ProcurementsPlanning

Conclusion
#

From the above table, you can observe that a CR is raised during the project execution or the M&C stage. To ensure that you don’t complicate the PICC process or increase the work of experts these processes need to be tuned in such a way that a sensible CR is raised. Another thing we need to keep in mind that when CR is not raised on time it is leaked as a defect in the product. The cost of not raising a CR on time can be costly when we need to fix something in a final product.

Dr. Hari Thapliyaal's avatar

Dr. Hari Thapliyaal

Dr. Hari Thapliyal is a seasoned professional and prolific blogger with a multifaceted background that spans the realms of Data Science, Project Management, and Advait-Vedanta Philosophy. Holding a Doctorate in AI/NLP from SSBM (Geneva, Switzerland), Hari has earned Master's degrees in Computers, Business Management, Data Science, and Economics, reflecting his dedication to continuous learning and a diverse skill set. With over three decades of experience in management and leadership, Hari has proven expertise in training, consulting, and coaching within the technology sector. His extensive 16+ years in all phases of software product development are complemented by a decade-long focus on course design, training, coaching, and consulting in Project Management. In the dynamic field of Data Science, Hari stands out with more than three years of hands-on experience in software development, training course development, training, and mentoring professionals. His areas of specialization include Data Science, AI, Computer Vision, NLP, complex machine learning algorithms, statistical modeling, pattern identification, and extraction of valuable insights. Hari's professional journey showcases his diverse experience in planning and executing multiple types of projects. He excels in driving stakeholders to identify and resolve business problems, consistently delivering excellent results. Beyond the professional sphere, Hari finds solace in long meditation, often seeking secluded places or immersing himself in the embrace of nature.

Comments:

Share with :

Related

Leadership Framework of Big MNCs
·279 words·2 mins· loading
Pmblog
Leadership Framework of Big MNCs # Microsoft # Microsoft’s leadership framework, introduced …
GenAI Usecases for Project Managers
·4151 words·20 mins· loading
Pmblog
GenAI Usecases for Project Managers # Introduction # GenAI is a major breakthrough in human …
Popular Business Process Frameworks
·2031 words·10 mins· loading
Pmblog
Popular Business Process Frameworks # What is business process framework? # Business process …
ZED Best Practices v2
·1337 words·7 mins· loading
Pmblog ZED Certification ZED Version 2 Zero Defect Zero Effect MSME QCI
ZED Best Practices Based on Version 2 # Introduction & Background # Objective # Adopt Best …
Agility vs Scale in Business
·1087 words·6 mins· loading
Pmblog Project Management
Agility vs Scale in Business # Recently I was watching a video about entrepreneurship. This was …